Library Updates

Library Rendering
Dates to Remember:
June 6th - Dewberry Architects will present the final plans to City Council 
June 7th - Advertising bids go out following City Council approval. 
July 5th - Bid openings scheduled 
July 18th - Construction contracts will be awarded @ Special meeting 
August 12th - Anticipated public ground breaking

The new 23,000 square foot library will include walking trails, pond improvements, a drive-through book return, additional/wider parking spaces, a new playground, extensive landscaping, large picture windows, a children’s area and a teen center, and outdoor reading porches. Construction will take about 12-18 months. The grand opening is currently set for Fall 2018. Plans and updates will be made available as they occur.

Design plans can be found HERE.